lightweight partition wall plate with Φ6mm or Φ8mm steel bar to the middle of the lightweight partition wall plate at 45 degrees into the bottom with "7" type rebar one end into the concrete foundation, one end into the wall plate.
Hammer, Trowel, electric circular saw,electric drill, Infrared level instrument, ruler
Accessories:
Wooden wedge, steel bar, anti-crack tape, cement mortar
Step1 Setting line, and lift the wall panels and installation accessories to the location ready for install
Step2 Applying cement mortar, apply ZJT specific cement mortar to the floor and the groove of wall panel
Step3 Installation wall panel. Assemble the cement mortar filled wall panels into the right position, level from the bottom of the wallboard with a gauging trowel, make it tight, temporarily fixed with wooden wedges, using"L" type steel bar to reinforce the wall panel and floor or ceiling
Step4 Cutting, using a electric saw cut the size you needed, length 180*6mm steel bars are required to enter from the 45-degree
Step5 Correcting.Plane correction with a ruler
Step6 Grouting, filling up cement mortar
Step7 Sticking Anti-Crack Tape
Step8 Slotting and Wiring, setting lines on places needing to set with concealed wire and switch box, then cut a groove by the electric saw, filling with specific mortar after installation
Step9 Installation door frame and wall frame.Reserve enough space according to the size of the door and window, then install the wall panel
Step10 Decorating the wall surface directly by plaster, wallpaper, tiles and other painting
(If the height of the wall exceeds 6m, and the length of the wall exceeds 8m, the square bar, H bar or channel steel should be added correspondingly to strengthen the joint)